Presented by:
         Sanjaya Dhungel (WECS)
 Binay Charan Shrestha (DUDBC)
  Dilip Kumar Sadaula (DSCWM)
    Kamaldeo Prasad Shah (DoR)
Mahendra Dhose Adhikari (MoHP)
    Rudra Nath Devkota (MoHA)
Background of the Study     Sanjaya Dhungel

Introduction of Organization Binay Charan Shrestha


Data Presentation &         Dilip Kumar Sadaula
Analysis                    Kamaldeo Prasad Shah


Major findings, Conclusion & Mahendra Dhose Adhikari
Recommendation               Rudra Nath Devkota
Sanjaya Dhungel
(WECS)
Settlement Status:
total population: 26,494,504
        Male         48.50%
        Female       51.50%

Households 5,423,297
Own house 85.26%
Rented houses    12.81%

Total number of houses/buildings and
residential structures    4,768,196.
Need for the Apartments:
In Urban Areas
- Development
- Job Opportunities
- Physical Facilities
- Unable to spend time for construction
- Trends of Nucleus Families
Business Opportunities:
-   Developers
-   Financial Institutions
-   Manufacturers
Apartment Construction Process:

Players:

-   Individuals
-   Developers
-    Financial Institutions
-    Manufacturers
Apartment Construction Process:

 Regulating Agencies:
- Municipalities, VDCs
- Ministry of Science, Technology and
   Environment
- Kathmandu Valley Development Authority
- Civil Aviation Authority
- Kathmandu Valley Water Supply and
   Management Board
- Department of Urban Development and
   Building Construction
Objective of the Study

General Objective:
- To review the Process adopted for construction
  of the apartments in Kathmandu Valley

Specific Objective:
- Assess the apartment building approval
  procedure
- Examine the monitoring and supervision as
  practices by DUDBC
Methodology



-   Information Collection
-   Visit the apartments
-   Analysis
-   Findings
Limitations
• The present study is mainly based on secondary
   data / information collected from DUDBC, DOK.

•   Review of apartment construction approval
    procedure is mainly focused on the role of
    DUDBC, DOK.

•   The primary information collected is from one
    apartment (10 residential units) only and may not
    represent the case of all the apartments. It is of
    qualitative type and only subjective inferences
    have been made.
Binay Charan Shrestha
(DUDBC)
2057
                        2045        DUDBC

               2028      DoB/DHUD
               DoHBPP
        2020
         DoB
 1970
Banaune Adda
Major Sectors

  -   Urban Planning

      -   Achieve a balanced national urban structure, Promote
          safe and economically vibrant urban environment and
          Promote effective urban management.
  -   Housing
      -   Promote Planned Development through providing
          affordable, adequate and safe shelter to all income
          group people.
  -   Buildings
      -   Promote safe, economical and Environment friendly
          buildings that can display indigenous architecture
Disaster Risk Reduction (Pre & Post Disaster)


  Flagship 1: School and hospital safety
  • Structural and non-structural aspects of making
     schools and hospitals earthquake resilient
  Flagship 2: Emergency preparedness and response
  capacity
  • Prepare site inventory of major open spaces to
     enhance preparedness of GoN & international
     agencies - includes camp management plan, primary
     health and school lifeline structures.
  • Municipal Profiles in terms of Earthquake Risk and
     Vulnerability, Vulnerability and Damage
     Assessment.
Disaster Risk Reduction (Pre & Post Disaster)


  Flagship 5: Policy/institutional support for disaster risk
  management
  • Preparation of Risk Hazard & GIS map of
     municipalities.
  • Study of Existing Practices in High Rise Building &
     Recommendation for safety.
  • Support to municipalities on Building code
     implementation & Update of Nepal National
     Building Code
  • Seismic Vulnerability Evaluation Guideline for
     Private and Public Building / Training Manual /
     Training on Damage & Vulnerability
     Assessment, Demonstrative Retrofitting works
Organization




 -   3 divisions
 -   24 division offices
 -   1 Maintenance division
 -   1 Training Center
Jurisdiction of DO
Vision

•   Urban Development Sector: Achieve a balanced
    national urban structure, Promote safe and
    economically vibrant urban environment and
    Promote effective urban management.

•   Housing Sector: Promote Planned Development
    through providing affordable, adequate and safe
    shelter to all income group people.

•   Building: Promote safe, economical and
    Environment friendly buildings that can display
    indigenous architecture
Mission

• To regulate and facilitate planned urban development
    in the municipalities and small towns and market
    centers.
•   To facilitate urban upgradation including
    environmental improvement of existing settlements.
•   To facilitate delivery of developed housing plots.
•   To conserve and develop cultural and religious sites
    through Local Area Planning.
•   To design and build public buildings as per national
    building code and conduct research and development
    of building technology.
Objective

Urban Development
• To invest in urban infrastructure and other services
  through inter-agency coordination,
• To empower and institutionally strengthen local
  bodies in order to build a clean, safe and prosperous
  urban environment,
• To progressively guide rural settlements towards
  urbanization by expanding rural urban inter-
  relationship under the overall notion that urban
  development promotes rural development.
Objective

Housing
• To provide safe and economical housing facility by
  developing organized habitats under the notion of
  “shelter for all”.
Building
• To construct and develop buildings which portray
  Nepalese architecture to the extent possible, and are
  safe, affordable and environmental friendly.
Dilip Sadaula
(DSCWM)
BACKGROUND

 TITLE OF GROUP WORK: "PRESENT STATUS OF
  APPARTMANT BUILDING APPROVAL AND
  CONSTUCTION IN KATHMANDU VALLEY"
 STUDY MAINLY BASED ON SECONDARY DATA
  COLLECTED FROM KATHMANDU DIVISION OFFICE OF
  DEPARTMANT OF URBAN DEVELOPMENT AND
  BUILDING CONSTRUCTION (DOK, DUDBC)
 SOME PRIMARY DATA ALSO COLECTED
   DISCUSSION WITH DOK ENGINEERS
   FIELD OBSERVATION OF KALASH APARTMENT
   INTERACTION WITH THE RESIDENTS OF THE KALASH
   APARTMENT
BRIEF HISTORY OF APARTMENT
CONSTRUCTION IN KATHMANDU VALLEY

 Joint housing felt necessary during 50s (B.S.) due
  to increased population pressure resulting in
  increase land price
 Enacted Ownership of Joint Housing Act
  (OJHA), 2054
 Approved Ownership of Joint Housing
  Regulation (OJHR), 2060
 Indreni Apartment-1, Bhatabhateni-first to
  obtain approval from DOK,DUDBC
STATUS OF APPROVED APARTMENTS
(Till poush 2069)

S. No Status of Apartment                             Number
1       On operation with completion certificate      13
2       On operation without completion certificate   15

3       On construction phase and others*             28
4       Construction not started                      8
        Total                                         64
 Source: DOK,DUDBC
On construction phase and others*
•Revised approval (3)
•Completion certificate processing (3)
•On construction (regular/irregular)
•Halt construction
LOCATION OF APPROVED APARTMENTS




   Source: DOK,DUDBC
APARTMENT LOCATION AND UNIT
DETAIL

Location            Nos   Units
Inside ring road    51    2862
Outside ring road   13    3465
Total               64    6327


Source: DOK,DUDBC
Source: DOK,DUDBC
Apartment proposals on approval process


S.   Status of Proposal                             No of apartment
No
1    Apartment proposal with regular follow up      6
2    Apartment proposal without regular follow up   8
3    Apartment proposal yet to apply for design     7
     approval
     Total                                          21

Source: DOK,DUDBC
APARTMENT APPROVAL PROCEDURE

                                         Develop Planning Permit
                                          Design and Drawings

   Environmental Assessment from line                                  Planning Permit from KVDA
   Ministry or Ministry of Environment

                                    Apartment approval from Division Office,            Approval from KVWSMB for
                                     DUDBC for Joint Apartment Act 2054
                                                                                            Ground water use

   Civil Aviation Authority
     for safe flying zone



                                         Approval from Local Government
                                               (Municipality/ VDC)

                                    Start the construction work according to
                                              approved plan/design


                                   Monitoring /Supervision from concerned
                                                 authorities


                                    Completion Certificate from concerned
                                                authorities

  Modified from: DOK,DUDBC
3 STAGES OF APARTMENT APPROVAL
PROCESS
 Stage 1: Planning Permit Stage
 Proponent develops project proposal with planning permit
    design and drawings
   Proponent applies for planning permit from KVDA
   Proponent undertakes environmental screening
   Stage 2: Apartment Approval Stage
   Applies for building permit and apartment approval from
    division office, DUDBC
   Undertakes EIA/IEE study as required
   Applies for clearance from civil aviation authority for safe
    flying zone
   Applies for approval from KVWSMB for groundwater use
   Stage 3: Local Body Approval Stage
   Applies for approval from municipality/VDC concerned
Kamaldeo Prasad Shah
(DoR)
PLANNING PERMIT

 KVDA reviews the documents within the broad
 framework

   Town Development Act, 2045


   Gazette Published on 2062/11/22


   Building bylaws 2064
Key Elements Covered by Planning Permit

 Ground coverage area
 FAR
 Distance between block
 Parking facilities
 Sewer, electrical systems, water supply plan
 Waste water and solid waste management etc
Environmental Approval


 Developer undertake EA as per Environment
  Protection Act 2053 & EPR 2055.
 The screening criteria are as mentioned in the
  following table .
 The developer conducts either IEE or EIA and
  submits to MoUD in case of IEE and MoSTE in
  case of EIA
ENVIRONMENTAL APPROVAL
                    Contd.

S.N      Criteria        No EA       IEE         EIA


1     Built Up Area <5000        5000-10000   >10000
                    Sqm          Sqm          Sqm
2     No of storey <10           10-16        >16

3     Ht. of        the <25 m    25-50 m      >50 m
      building

4     No of inflow <1000         1000-2000    >2000
      & outflow at a persons     persons      persons
      time
APARTMENT APPROVAL ELEMENTS
 Broad Framework  KEY
  OJHA 2054 & OJHR 2060    ARCHITECTURAL
                             DESIGN
  BUILDING ACT 2055            Staircase, Exit
                            STRUCTURAL DESIGN
                              Geo-technical Investigation
  NEPAL NATIONAL
  BUILDING CODE 2060        SANITARY, WATER
                             SUPPLY AND
                             PLANNING SYSTEM
  WORK PROCEDURE               WS/Treatment
  2060                           Plant/Pumping System
                            FIRE FIGHTING SYSTEM
                              Firefighting hose reels
APARTMENT APPROVAL Contd

 Presentation for complex structure
 Review by “expert panel” for complex structure
 The docs to be submitted for approval
    Provisions of details of services/facilities


   QA docs and designer’s affidavit papers


   Project brief reports, design report & soil test report


   Insurance letter
Monitoring and Supervision
 Checking of reinforcement detailing


 Periodic progress reports and Lab reports.


 Weak monitoring from KVDA and Local bodies


 Diversified observations made by DOK.
Use of bamboo scaffoldings and safety net a threat to
                      safety
Building bylaws violations
Alteration in Column, Beam size
Safety Measures for worker ???
Improper Use of Safety Tools
Use Change without prior approval
Issuance of Completion Certificate

 Project Developer submits
   As Built Drawings
   Quality Control Reports
   Environmental compliance Report
• DOK undertake final checking
• Hiring of Third Party Consultant
• Completion Certificate Issued
Apartment Living Condition
 9 stories, 75 Units, Mostly
    Businessman
   Functioning since 2 yrs
   Unaware with OJHA 2054
    & OJHR 2060
   Till date no unit ownership
    has been transferred
   Without PAN Number
   Lack of sufficient open
    space
   Lack of sufficient space for
    gathering during
    emergency
Apartment Living Condition
 9 stories, 75 Units, Mostly Businessman
 Functioning since 2 yrs
 Unaware with OJHA 2054 & OJHR 2060
 Till date no unit ownership has been transferred
 Without PAN Number
 Lack of sufficient open space
 Lack of sufficient space for gathering during
 emergency
A Visit to Kalash Apartment, Tahachal
Mahendra Dhose Adhikari
(MoHP)
KEY ISSUES
1. Time Taken for Approval Process.
      Inadequacy of technical manpower in KD.
      Developer’s unwillingness to obtain design approval
      Involvement of different agencies in approval
       process(at least six).
2. Project Management .
   •   Frequent change of technical personnel.
   •   Weaker coordination.
   •   Improper and inadequate safety consideration during
       construction.
•   Weak progress reporting



•   Construction without prior checking by
    DOK.



•   Use change without prior approval.
3.Insufficient Resources
    •    DOK have old organogram but increased work
        load
    •   Lack of budget and vehicle for monitoring.

4.Unethical Practice
•      Designer change ( one person designed the
    other signed and affidavit )
MAJOR FINDINGS
• Apartment    approval process is a        multi
 stakeholder task . DOK has a key role.



• Time taken for getting apartment approval is
  varying (6m-3 yrs.) depend on different factors.



• Insufficient resources in DOK.
• Some    apartments are in operation and
 ownership       transfer   without    completion
 certificate, user change having no permission.

• Weak Project management and ethical issues has
  been emerged during last 8-9 years period.

• The residents of surveyed apartment (Kalash)
  are unaware on exiting apartment law and
  regulation. They have no ownership certificate
  till now.
Rudra Nath Devkota
(MoHA)
BACKGROUND
 TITLE OF GROUP WORK: "PRESENT STATUS OF
  APPARTMANT BUILDING APPROVAL AND
  CONSTUCTION IN KATHMANDU VALLEY"
 STUDY MAINLY BASED ON SECONDARY DATA
  COLLECTED FROMD KATHMANDU DIVISION
  OFFICE OF DEPARTMANT OF URBAN
  DEVELOPMENT AND BUILDING CONSTRUCTION
  (DOK, DUDBC)
 SOME PRIMARY DATA ALSO COLECTED
    DISCUSSION WITH DOK ENGINEERS
    FIELD OBSERVATION OF KALASH APARTMENT
    INTERACTION WITH THE RESIDENTS OF THE
     KALASH APARTMENT
CONCLUSION

  In general, apartment approval and
 construction has been found to be
 streamlined in the right direction.
 However the pertinent issues emerged so
 far have to be systematically and
 promptly addressed by the concerned
 authority(ies). DOK has to be
 strengthened. Safety considerations have
 to be given the first priority by all
 stakeholders concerned.
ESSENCE OF CONCLUSION

 Apartment approval and construction
  streamlined
 Pertinent issues to be addressed
 DOK to be strengthened
 Safety to be given the first priority
RECOMMENDATION-1

 DOK should be strengthened by
allocating adequate resources and
providing additional responsibilities and
authorities so that it can function as a
strong and competent " one door" of the
government in apartment housing sector.
RECOMMENDATION-2

 DOK and the concerning local authority
(municipality/VDC) should organize
regular safety awareness campaign
(including drilling) in the occupied
apartments. Safety related
systems/equipments should be checked
on a regular basis.
RECOMMENDATION-3

Third party monitoring can be introduced
after required preparations. This will help
in ensuring better adoption of safety
requirements while keeping the DOK size
appropriately slim.
Present status of apartment building approval and construction
Present status of apartment building approval and construction

More Related Content

Similar to Present status of apartment building approval and construction

FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxArJayTambaoan
 
Design approval procedure
Design approval procedureDesign approval procedure
Design approval procedureIqbál Ãzàm
 
Summary of NBC 2016
Summary of NBC 2016Summary of NBC 2016
Summary of NBC 2016ssuserfa2cfd
 
Compendium_for_Design_of_Central_Government_Housing.pdf
Compendium_for_Design_of_Central_Government_Housing.pdfCompendium_for_Design_of_Central_Government_Housing.pdf
Compendium_for_Design_of_Central_Government_Housing.pdfDineshReddyManchala1
 
Hatem El Karnshawy . BSc, PMP, MASCE
Hatem El Karnshawy . BSc, PMP, MASCEHatem El Karnshawy . BSc, PMP, MASCE
Hatem El Karnshawy . BSc, PMP, MASCEenghatem
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14Competition Advisory Services (India) LLP
 
Real estate hrm ppt final naveen shukla
Real estate hrm ppt final naveen shuklaReal estate hrm ppt final naveen shukla
Real estate hrm ppt final naveen shuklaNaveen Shukla
 
Item # 7 - Katherine Ct (Final Review)
Item # 7 - Katherine Ct (Final Review)Item # 7 - Katherine Ct (Final Review)
Item # 7 - Katherine Ct (Final Review)ahcitycouncil
 
supreme court additonal complex project
supreme court additonal complex projectsupreme court additonal complex project
supreme court additonal complex projectAbhishek singh
 
Site analysis and documentation
Site analysis and documentation Site analysis and documentation
Site analysis and documentation Lawin Langat
 
Kick-Off Meeting Habibiyyah (FINAL).pdf
Kick-Off Meeting Habibiyyah (FINAL).pdfKick-Off Meeting Habibiyyah (FINAL).pdf
Kick-Off Meeting Habibiyyah (FINAL).pdfMOHDFIRRDHAUSBINMOHD
 

Similar to Present status of apartment building approval and construction (20)

FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptx
 
Design approval procedure
Design approval procedureDesign approval procedure
Design approval procedure
 
Summary of NBC 2016
Summary of NBC 2016Summary of NBC 2016
Summary of NBC 2016
 
CV 2018 Series
CV 2018 SeriesCV 2018 Series
CV 2018 Series
 
PPT to BPC.pptx
PPT to BPC.pptxPPT to BPC.pptx
PPT to BPC.pptx
 
Compendium_for_Design_of_Central_Government_Housing.pdf
Compendium_for_Design_of_Central_Government_Housing.pdfCompendium_for_Design_of_Central_Government_Housing.pdf
Compendium_for_Design_of_Central_Government_Housing.pdf
 
ST-Decision Support System
ST-Decision Support SystemST-Decision Support System
ST-Decision Support System
 
Hatem El Karnshawy . BSc, PMP, MASCE
Hatem El Karnshawy . BSc, PMP, MASCEHatem El Karnshawy . BSc, PMP, MASCE
Hatem El Karnshawy . BSc, PMP, MASCE
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
 
Real estate hrm ppt final naveen shukla
Real estate hrm ppt final naveen shuklaReal estate hrm ppt final naveen shukla
Real estate hrm ppt final naveen shukla
 
Item # 7 - Katherine Ct (Final Review)
Item # 7 - Katherine Ct (Final Review)Item # 7 - Katherine Ct (Final Review)
Item # 7 - Katherine Ct (Final Review)
 
Test
TestTest
Test
 
supreme court additonal complex project
supreme court additonal complex projectsupreme court additonal complex project
supreme court additonal complex project
 
Site analysis and documentation
Site analysis and documentation Site analysis and documentation
Site analysis and documentation
 
Redevelopment
RedevelopmentRedevelopment
Redevelopment
 
Resume
ResumeResume
Resume
 
Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
Norhtern Power Distribution Project
Norhtern Power Distribution ProjectNorhtern Power Distribution Project
Norhtern Power Distribution Project
 
Kick-Off Meeting Habibiyyah (FINAL).pdf
Kick-Off Meeting Habibiyyah (FINAL).pdfKick-Off Meeting Habibiyyah (FINAL).pdf
Kick-Off Meeting Habibiyyah (FINAL).pdf
 
Webinar on Town planning scheme
Webinar on Town planning schemeWebinar on Town planning scheme
Webinar on Town planning scheme
 

Present status of apartment building approval and construction

  • 1. Presented by: Sanjaya Dhungel (WECS) Binay Charan Shrestha (DUDBC) Dilip Kumar Sadaula (DSCWM) Kamaldeo Prasad Shah (DoR) Mahendra Dhose Adhikari (MoHP) Rudra Nath Devkota (MoHA)
  • 2. Background of the Study Sanjaya Dhungel Introduction of Organization Binay Charan Shrestha Data Presentation & Dilip Kumar Sadaula Analysis Kamaldeo Prasad Shah Major findings, Conclusion & Mahendra Dhose Adhikari Recommendation Rudra Nath Devkota
  • 4. Settlement Status: total population: 26,494,504 Male 48.50% Female 51.50% Households 5,423,297 Own house 85.26% Rented houses 12.81% Total number of houses/buildings and residential structures 4,768,196.
  • 5. Need for the Apartments: In Urban Areas - Development - Job Opportunities - Physical Facilities - Unable to spend time for construction - Trends of Nucleus Families
  • 6. Business Opportunities: - Developers - Financial Institutions - Manufacturers
  • 7. Apartment Construction Process: Players: - Individuals - Developers - Financial Institutions - Manufacturers
  • 8. Apartment Construction Process: Regulating Agencies: - Municipalities, VDCs - Ministry of Science, Technology and Environment - Kathmandu Valley Development Authority - Civil Aviation Authority - Kathmandu Valley Water Supply and Management Board - Department of Urban Development and Building Construction
  • 9. Objective of the Study General Objective: - To review the Process adopted for construction of the apartments in Kathmandu Valley Specific Objective: - Assess the apartment building approval procedure - Examine the monitoring and supervision as practices by DUDBC
  • 10. Methodology - Information Collection - Visit the apartments - Analysis - Findings
  • 11. Limitations • The present study is mainly based on secondary data / information collected from DUDBC, DOK. • Review of apartment construction approval procedure is mainly focused on the role of DUDBC, DOK. • The primary information collected is from one apartment (10 residential units) only and may not represent the case of all the apartments. It is of qualitative type and only subjective inferences have been made.
  • 13. 2057 2045 DUDBC 2028 DoB/DHUD DoHBPP 2020 DoB 1970 Banaune Adda
  • 14. Major Sectors - Urban Planning - Achieve a balanced national urban structure, Promote safe and economically vibrant urban environment and Promote effective urban management. - Housing - Promote Planned Development through providing affordable, adequate and safe shelter to all income group people. - Buildings - Promote safe, economical and Environment friendly buildings that can display indigenous architecture
  • 15. Disaster Risk Reduction (Pre & Post Disaster) Flagship 1: School and hospital safety • Structural and non-structural aspects of making schools and hospitals earthquake resilient Flagship 2: Emergency preparedness and response capacity • Prepare site inventory of major open spaces to enhance preparedness of GoN & international agencies - includes camp management plan, primary health and school lifeline structures. • Municipal Profiles in terms of Earthquake Risk and Vulnerability, Vulnerability and Damage Assessment.
  • 16. Disaster Risk Reduction (Pre & Post Disaster) Flagship 5: Policy/institutional support for disaster risk management • Preparation of Risk Hazard & GIS map of municipalities. • Study of Existing Practices in High Rise Building & Recommendation for safety. • Support to municipalities on Building code implementation & Update of Nepal National Building Code • Seismic Vulnerability Evaluation Guideline for Private and Public Building / Training Manual / Training on Damage & Vulnerability Assessment, Demonstrative Retrofitting works
  • 17. Organization - 3 divisions - 24 division offices - 1 Maintenance division - 1 Training Center
  • 19. Vision • Urban Development Sector: Achieve a balanced national urban structure, Promote safe and economically vibrant urban environment and Promote effective urban management. • Housing Sector: Promote Planned Development through providing affordable, adequate and safe shelter to all income group people. • Building: Promote safe, economical and Environment friendly buildings that can display indigenous architecture
  • 20. Mission • To regulate and facilitate planned urban development in the municipalities and small towns and market centers. • To facilitate urban upgradation including environmental improvement of existing settlements. • To facilitate delivery of developed housing plots. • To conserve and develop cultural and religious sites through Local Area Planning. • To design and build public buildings as per national building code and conduct research and development of building technology.
  • 21. Objective Urban Development • To invest in urban infrastructure and other services through inter-agency coordination, • To empower and institutionally strengthen local bodies in order to build a clean, safe and prosperous urban environment, • To progressively guide rural settlements towards urbanization by expanding rural urban inter- relationship under the overall notion that urban development promotes rural development.
  • 22. Objective Housing • To provide safe and economical housing facility by developing organized habitats under the notion of “shelter for all”. Building • To construct and develop buildings which portray Nepalese architecture to the extent possible, and are safe, affordable and environmental friendly.
  • 24. BACKGROUND  TITLE OF GROUP WORK: "PRESENT STATUS OF APPARTMANT BUILDING APPROVAL AND CONSTUCTION IN KATHMANDU VALLEY"  STUDY MAINLY BASED ON SECONDARY DATA COLLECTED FROM KATHMANDU DIVISION OFFICE OF DEPARTMANT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION (DOK, DUDBC)  SOME PRIMARY DATA ALSO COLECTED  DISCUSSION WITH DOK ENGINEERS  FIELD OBSERVATION OF KALASH APARTMENT  INTERACTION WITH THE RESIDENTS OF THE KALASH APARTMENT
  • 25. BRIEF HISTORY OF APARTMENT CONSTRUCTION IN KATHMANDU VALLEY  Joint housing felt necessary during 50s (B.S.) due to increased population pressure resulting in increase land price  Enacted Ownership of Joint Housing Act (OJHA), 2054  Approved Ownership of Joint Housing Regulation (OJHR), 2060  Indreni Apartment-1, Bhatabhateni-first to obtain approval from DOK,DUDBC
  • 26. STATUS OF APPROVED APARTMENTS (Till poush 2069) S. No Status of Apartment Number 1 On operation with completion certificate 13 2 On operation without completion certificate 15 3 On construction phase and others* 28 4 Construction not started 8 Total 64 Source: DOK,DUDBC On construction phase and others* •Revised approval (3) •Completion certificate processing (3) •On construction (regular/irregular) •Halt construction
  • 27. LOCATION OF APPROVED APARTMENTS Source: DOK,DUDBC
  • 28. APARTMENT LOCATION AND UNIT DETAIL Location Nos Units Inside ring road 51 2862 Outside ring road 13 3465 Total 64 6327 Source: DOK,DUDBC
  • 30. Apartment proposals on approval process S. Status of Proposal No of apartment No 1 Apartment proposal with regular follow up 6 2 Apartment proposal without regular follow up 8 3 Apartment proposal yet to apply for design 7 approval Total 21 Source: DOK,DUDBC
  • 31. APARTMENT APPROVAL PROCEDURE Develop Planning Permit Design and Drawings Environmental Assessment from line Planning Permit from KVDA Ministry or Ministry of Environment Apartment approval from Division Office, Approval from KVWSMB for DUDBC for Joint Apartment Act 2054 Ground water use Civil Aviation Authority for safe flying zone Approval from Local Government (Municipality/ VDC) Start the construction work according to approved plan/design Monitoring /Supervision from concerned authorities Completion Certificate from concerned authorities Modified from: DOK,DUDBC
  • 32. 3 STAGES OF APARTMENT APPROVAL PROCESS  Stage 1: Planning Permit Stage  Proponent develops project proposal with planning permit design and drawings  Proponent applies for planning permit from KVDA  Proponent undertakes environmental screening  Stage 2: Apartment Approval Stage  Applies for building permit and apartment approval from division office, DUDBC  Undertakes EIA/IEE study as required  Applies for clearance from civil aviation authority for safe flying zone  Applies for approval from KVWSMB for groundwater use  Stage 3: Local Body Approval Stage  Applies for approval from municipality/VDC concerned
  • 34. PLANNING PERMIT  KVDA reviews the documents within the broad framework  Town Development Act, 2045  Gazette Published on 2062/11/22  Building bylaws 2064
  • 35. Key Elements Covered by Planning Permit  Ground coverage area  FAR  Distance between block  Parking facilities  Sewer, electrical systems, water supply plan  Waste water and solid waste management etc
  • 36. Environmental Approval  Developer undertake EA as per Environment Protection Act 2053 & EPR 2055.  The screening criteria are as mentioned in the following table .  The developer conducts either IEE or EIA and submits to MoUD in case of IEE and MoSTE in case of EIA
  • 37. ENVIRONMENTAL APPROVAL Contd. S.N Criteria No EA IEE EIA 1 Built Up Area <5000 5000-10000 >10000 Sqm Sqm Sqm 2 No of storey <10 10-16 >16 3 Ht. of the <25 m 25-50 m >50 m building 4 No of inflow <1000 1000-2000 >2000 & outflow at a persons persons persons time
  • 38. APARTMENT APPROVAL ELEMENTS  Broad Framework  KEY  OJHA 2054 & OJHR 2060  ARCHITECTURAL DESIGN  BUILDING ACT 2055  Staircase, Exit  STRUCTURAL DESIGN  Geo-technical Investigation  NEPAL NATIONAL BUILDING CODE 2060  SANITARY, WATER SUPPLY AND PLANNING SYSTEM  WORK PROCEDURE  WS/Treatment 2060 Plant/Pumping System  FIRE FIGHTING SYSTEM  Firefighting hose reels
  • 39. APARTMENT APPROVAL Contd  Presentation for complex structure  Review by “expert panel” for complex structure  The docs to be submitted for approval  Provisions of details of services/facilities  QA docs and designer’s affidavit papers  Project brief reports, design report & soil test report  Insurance letter
  • 40. Monitoring and Supervision  Checking of reinforcement detailing  Periodic progress reports and Lab reports.  Weak monitoring from KVDA and Local bodies  Diversified observations made by DOK.
  • 41. Use of bamboo scaffoldings and safety net a threat to safety
  • 44. Safety Measures for worker ???
  • 45. Improper Use of Safety Tools
  • 46. Use Change without prior approval
  • 47. Issuance of Completion Certificate  Project Developer submits  As Built Drawings  Quality Control Reports  Environmental compliance Report • DOK undertake final checking • Hiring of Third Party Consultant • Completion Certificate Issued
  • 48. Apartment Living Condition  9 stories, 75 Units, Mostly Businessman  Functioning since 2 yrs  Unaware with OJHA 2054 & OJHR 2060  Till date no unit ownership has been transferred  Without PAN Number  Lack of sufficient open space  Lack of sufficient space for gathering during emergency
  • 49. Apartment Living Condition  9 stories, 75 Units, Mostly Businessman  Functioning since 2 yrs  Unaware with OJHA 2054 & OJHR 2060  Till date no unit ownership has been transferred  Without PAN Number  Lack of sufficient open space  Lack of sufficient space for gathering during emergency
  • 50. A Visit to Kalash Apartment, Tahachal
  • 52. KEY ISSUES 1. Time Taken for Approval Process.  Inadequacy of technical manpower in KD.  Developer’s unwillingness to obtain design approval  Involvement of different agencies in approval process(at least six). 2. Project Management . • Frequent change of technical personnel. • Weaker coordination. • Improper and inadequate safety consideration during construction.
  • 53.
  • 54. Weak progress reporting • Construction without prior checking by DOK. • Use change without prior approval.
  • 55.
  • 56. 3.Insufficient Resources • DOK have old organogram but increased work load • Lack of budget and vehicle for monitoring. 4.Unethical Practice • Designer change ( one person designed the other signed and affidavit )
  • 57. MAJOR FINDINGS • Apartment approval process is a multi stakeholder task . DOK has a key role. • Time taken for getting apartment approval is varying (6m-3 yrs.) depend on different factors. • Insufficient resources in DOK.
  • 58. • Some apartments are in operation and ownership transfer without completion certificate, user change having no permission. • Weak Project management and ethical issues has been emerged during last 8-9 years period. • The residents of surveyed apartment (Kalash) are unaware on exiting apartment law and regulation. They have no ownership certificate till now.
  • 60. BACKGROUND  TITLE OF GROUP WORK: "PRESENT STATUS OF APPARTMANT BUILDING APPROVAL AND CONSTUCTION IN KATHMANDU VALLEY"  STUDY MAINLY BASED ON SECONDARY DATA COLLECTED FROMD KATHMANDU DIVISION OFFICE OF DEPARTMANT OF URBAN DEVELOPMENT AND BUILDING CONSTRUCTION (DOK, DUDBC)  SOME PRIMARY DATA ALSO COLECTED  DISCUSSION WITH DOK ENGINEERS  FIELD OBSERVATION OF KALASH APARTMENT  INTERACTION WITH THE RESIDENTS OF THE KALASH APARTMENT
  • 61. CONCLUSION In general, apartment approval and construction has been found to be streamlined in the right direction. However the pertinent issues emerged so far have to be systematically and promptly addressed by the concerned authority(ies). DOK has to be strengthened. Safety considerations have to be given the first priority by all stakeholders concerned.
  • 62. ESSENCE OF CONCLUSION  Apartment approval and construction streamlined  Pertinent issues to be addressed  DOK to be strengthened  Safety to be given the first priority
  • 63. RECOMMENDATION-1 DOK should be strengthened by allocating adequate resources and providing additional responsibilities and authorities so that it can function as a strong and competent " one door" of the government in apartment housing sector.
  • 64. RECOMMENDATION-2 DOK and the concerning local authority (municipality/VDC) should organize regular safety awareness campaign (including drilling) in the occupied apartments. Safety related systems/equipments should be checked on a regular basis.
  • 65. RECOMMENDATION-3 Third party monitoring can be introduced after required preparations. This will help in ensuring better adoption of safety requirements while keeping the DOK size appropriately slim.